ALKHOBAR: Saudi Aramco has extended the deadline for companies to bid for construction of a clean fuels and aromatics project at its largest refinery in Ras Tanura, three industry sources said.
Bids are now due by Oct. 20, pushed back from Sept. 8, for the multi-billion-dollar project.
“Bidders requested an extension as there were so many additions to the scope of work,” one of the sources said.
Saudi Aramco has embarked on a program to upgrade its refineries as part of a shift by Middle Eastern refiners to produce cleaner fuels for export markets.
Aramco has also extended the date for bids to build a 2,400 megawatt power plant to supply electricity to its new 400,000 bpd refinery in Jizan, sources said, after companies asked for more time to prepare their offers.
The Ras Tanura clean fuels and aromatics project due on line by 2016 is part of Aramco’s second phase of its refineries upgrade. It will also help supply a new petrochemicals joint venture with Dow Chemical.
It includes a naphtha hydrotreater among other units and will have an annual production capacity of around 1 million metric tons of aromatics.
In March, Aramco shut its joint venture refinery with Exxon Mobil for nearly two months to bring a $2 billion clean fuels project on line.
The firm is building three new refineries in Saudi Arabia, one in the East with France’s Total, one near the Red Sea city of Yanbu with China’s Sinopec, and another at Jazan, near the border with Yemen. All will produce cleaner fuels and some petrochemicals.
The new power plant to supply the Jazan refinery will use integrated gasification combined cycle (IGCC) technology to convert vacuum residue fuel from the refinery into a synthetic gas.
Construction of the project is split into four parts. Bids for three have been extended to Oct. 9, while the remaining package known as the gasification unit is extended to Oct. 23.
The Jazan refinery, currently under construction, is likely to be delayed by six to 12 months, because work on associated infrastructure is behind schedule, sources said in July.